I setup a scheduler to remind me of recycle day, every other Wednesday. It used to work great, but the city changed the schedule. So, I attempted to change the task associated with the scheduler to match. No matter what I changes I make it shows the next will occur on Wed. Mar 25.

6861

Ron
March 18th, 2015, 01:21 PM
I think that field doesn't update until you re-open the dialog, sorry about that.

harleydude
March 18th, 2015, 01:58 PM
I have shutdown/restarted Girder, the same date is displayed. Mar 25.

Ron
March 18th, 2015, 02:29 PM
2 issues are running together here.

1. You ask to have this happen every two weeks, starting on 3/4 at noon.
2. The time of trigger is midnight Wednesday.

1+2 means that 3/4 is not the first trigger, but 11/4 is. ( noon start is after the trigger time of midnight )

Then you get a silly 1:00 time for the trigger instead of midnight, I have a feeling this is related to daylight savings shift in some form or other. Adding actual days to the QDateTime instead of 3600 * 24 * days seconds solved that one. The next release will have this fix.

harleydude
April 12th, 2015, 02:31 PM
Any update?

Ron
April 12th, 2015, 02:34 PM
Yes this is fixed. I'll try to get a release out this week. Things might actually be settling down here a bit. (famous last words)